C-29 Final Completion of Clay High School Buildings 1, 2, and 3 Electric Panels Replacement

Issue/Rationale

Establish a Final Completion date formally for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. This date is determined by the Project Manager in accordance with project documents.  Final Completion was achieved on September 16, 2010.

                                                                                   

The project, as determined by the Project Manager and Project Engineer (KPI Engineering, Inc.), has reached Final Complete in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a Final completion date must be formally established.



Recommended Action
Approve Final Completion

Financial Impact
None

Submitted By

Michael J. Elliott, Assistant Superintendent of Support Services

 

Data Source:

 

Facility Planning and Construction




Attachment:  CHS Electric Panels Replacement Final Completion.pdf